Posted by: Pdfprep Category: PMI-001 Tags: PMI Certification, PMI-001 exam questions, PMI-001 practice exam Post Date: October 15, 2020 Pdfprep2020-10-15T11:41:22+00:00 Which item is an input to the Define Activities process?A . Schedule dataB . Activity listC . Risk registerD . Scope baseline View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.