Posted by: Pdfprep Category: PRF Tags: PRF exam questions, PRF practice exam, PRINCE2 Foundation Post Date: November 25, 2020 Pdfprep2020-11-25T00:18:52+00:00 Which product is NOT created in the Managing a Stage Boundary process?A . Benefits Review PlanB . End Stage ReportC . Lessons ReportD . Exception Plan View Answer Answer: A Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.