Posted by: Pdfprep
Post Date: October 24, 2020
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,
A . benefits, progress, risk,
B . benefits, quality, risk,
C . change, quality, progress,
D . benefits, customers, quality,
Answer: B
Leave a Reply