Posted by: Pdfprep Category: PRINCE2 Tags: Polycom Certification, PRINCE2 exam questions, PRINCE2 practice exam Post Date: December 3, 2020 Pdfprep2020-12-03T08:54:52+00:00 Controlling a Stage process views the project from which role’s perspective?A . Team ManagerB . Project BoardC . Project AssuranceD . Project Manager View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.