Which statement is true about changing a project’s key?

Posted by: Pdfprep Category: ACP-100 Tags: , ,

Which statement is true about changing a project’s key?
A . Users have to update issue filters referencing the old project key.
B . Unshared project schemes will be automatically renamed to reflect the new project key.
C . External links to issues in that project need to be updated to match the new project key.
D . The old project key can be reused for a new project.
E . Internal Jira links referencing an old key will continue to work.

Answer: E

Explanation:

Reference: https://confluence.atlassian.com/adminjiraserver075/editing-a-project-key-935391076.html