Which resource informs a storage specialist if a Technical and Delivery Assessment (TDA) has to be done?
A . IBM Pre-sale TDA Checklist
B . Systems Assurance Product Review Guide
C . Trigger Criteria and Designated Product List
D . Digital Techline Center
Answer: A
Explanation:
The Technical Delivery Assessment (TDA) pre-installation checklist and worksheets document
provides several worksheets that the customer must complete for eachXIV
system. Use the worksheets to record information that is needed by the IBM
installation planning representative (IPR) andIBM service
representativeto install and configure theXIV system.
https://www.ibm.com/support/knowledgecenter/en/STJTAG/com.ibm.help.xivgen3.doc/Gen3/PG/xiv_pln3overview.html