Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

Which of the following would be most likely to assist when a customer has difficulty prioritizing stories?
A . Split the stories into smaller ones to allow the customer to choose the pieces that they want.
B . Have the team provide guidance into where their priorities lie to the customer.
C . Provide additional technical details to give the customer insight into technical challenges.
D . Have the team rewrite the stories with additional details to clarify requirements.

Answer: A