Posted by: Pdfprep
Post Date: January 29, 2021
An agile practitioner notices that team members are disengaged. As a result, the team’s velocity has decreased.
What should the agile practitioner do to get the team back on track?
A . Escalate the issue to the project sponsor.
B . Remove stories to increase velocity.
C . Hold a standup to address the issue.
D . Facilitate a team retrospective.
Answer: C
Leave a Reply