What estimation technique is an agile team using when collectively estimating the relative size of its stories using story points?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

What estimation technique is an agile team using when collectively estimating the relative size of its stories using story points?
A . Parametric
B . One-to-one comparison
C . Affinity
D . Planning poker

Answer: D

Explanation:

Reference: https://books.google.com.pk/books?id=TYoLAAAAQBAJ&pg=PA61&lpg=PA61&dq=scrum+estimation+technique+is+an+agile+team+using+when+collectively+estimating+the+relative+size+of+its+stories+using+story+points&source=bl&ots=MmVGsgmWXk&sig=ACfU3U2g­4srCxMdsi4DXwynCFrrvSBZow&hl=en&sa=X&ved=2ahUKEwj12IeO5t3pAhWURhUIHQUyDcwQ6AEwCXoECAoQAQ#v=onepage&q=scrum%20estimation%20technique%20is%20an%20agile%20team%20using %20when%20collectively%20estimating%20the%20relative%20size%20of%20its%20stories%20using% 20story%20points&f=false