What should the team do to effectively manage this?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

During an iteration, an agile team discovers infrastructure requirements that were not initially considered.

What should the team do to effectively manage this?
A . Rework the iteration scope to accommodate these requirements.
B . Add these requirements into the product backlog for future consideration.
C . Raise the discovery of these requirements as an issue, and escalate to management.
D . Immediately start working on these requirements.

Answer: C