A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint.
What should the team do?
A . Advise the product owner that the story will have to wait until the next sprint.
B . Work extra hours to complete the story and satisfy the customer’s requirements.
C . Break down the story into smaller increments and negotiate other stories on the sprint backlog.
D . Increase the length of the sprint to accommodate the story.
Answer: C