What should the team member do?

Posted by: Pdfprep Category: PMI-ACP Tags: , ,

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve.

What should the team member do?
A . Notify the product owner and begin resolution.
B . Communicate the issue to the team in the next stand up meeting.
C . Immediately begin resolution, and communicate it to the team during the retrospective.
D . Work on the next activity, and communicate it to the team during the retrospective.

Answer: B