Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.
What should the product owner do?
A . Terminate the project to cut losses
B . Review possible options and make an informed decision to cut losses based on delivered business value
C . Bring in experts to increase the probability of success
D . Continue the project, release the product without the failing feature, and fix the feature in a subsequent release
Answer: B