What should a team do when they complete all sprint goals earlier than expected?
A . Begin working on an item in the backlog
B . Ask the scrum master to select an item from the backlog on which to work
C . Ask the product owner to select an item from the backlog on which to work
D . Jointly decide with the scrum master on an item from the backlog on which to work
Answer: A