Two similar stories, A and B, are estimated at 3 story points. Story C, is estimated at 8 points. After an iteration in which A and C were completed, it is found that story A took much longer than story C.
What should the agile practitioner do?
A . Assign story B more than 8 story points so to provide a better estimate
B . Add points to story B’s iteration to account for the error but keep story B at 3 points
C . Assign more resources to story B to bring it in line with the estimate
D . Reestimate all stories including values for A, B and C
Answer: C