Posted by: Pdfprep
Post Date: November 20, 2020
An agile practitioner wants to ensure that stakeholders have current information about a project’s progress.
What should the agile practitioner do?
A . Regularly circulate an updated, detailed version of the project plan
B . Frequently update the online project management office (PMO) repository site
C . Invite the stakeholders to daily stand ups
D . Post a project board in an area where all can view it
Answer: D
Leave a Reply