Posted by: Pdfprep
Post Date: December 3, 2020
During a mature agile team’s planning meeting, a team member proposes a new framework that would considerably reduce implementation time.
However, the team lacks the confidence to try the new framework.
To help the team gain confidence, what should the agile practitioner suggest?
A . Develop a spike
B . Create an Ishikawa diagram
C . Perform a pre-mortem analysis
D . Complete a variance and trend analysis
Answer: D
Leave a Reply