Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations.
As a high-performance team, what should the team do?
A . Raise an impediment that resource tasks will be blocked, and notify the product owner
B . Ask the delivery manager for a temporary resource
C . Ask the scrum master to assign that team member’s tasks to the next available resource
D . Assume the team member’s tasks to meet iteration goals, and notify the product owner
Answer: C