At the end of each Sprint the Scrumboard is _________.
A . Updated with new tasks and completed tasks.
B . Placed besides the new one to compare team velocities in Sprints.
C . Analyzed by the Scrum master to understand the project progress in that particular sprint.
D . Reset or wiped off.
Answer: C
Explanation:
Reference: https://fitsmallbusiness.com/what-is-a-scrum-board/? __cf_chl_jschl_tk__=f53936a02af8b13a6c789509a9e50d80caf9db68-1579965118-0AX8DQIwPUTwHssRinUC0HBs1y0G4cueRRcNpGOdv3upGebf3xhz6sZtrd3r_e8p2LCAKsOhNtvMe1BjqhYqPiFFr1H832NeKyU9aTS7hOHZLRq68r12ibXnfqveWkOuTmmkUy0lhkGM2jWr8 w-7OODeTjry5BdCU0qCXv-ci8Kv6-QAHh8LizLiiZ9a7fBSzwcw15OkMbF6N6O3GdgjoKH48pvA7BxNqQIfxXxSaAPc7PSgiP4JNyrYhJsGWryQdu6msOKQXrxt4sa0Dl9UEwRyjyGzD_Nyzy7_qmwi5z