A company has replicated their critical application VMs to a second data center in another region. Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs.
What needs to be configured in Veeam to prepare for a disaster recovery situation?
A . Use a failover plan
B . Use a planned failover
C . Use Instant VM Recovery
D . Use on-click failover
Answer: C
Explanation:
Reference: https://www.veeam.com/virtual-machine-backup-solution-free.html