What is the correct job plan sequence that needs to be used?

Posted by: Pdfprep Category: C2010-555 Tags: , ,

An asset requires maintenance on a monthly, quarterly and annual basis. Three job plans have been created to meet this requirement called MONTHLY, QUARTERLY and ANNUAL.

What is the correct job plan sequence that needs to be used?
A . MONTHLY=1, QUARTERLY=4, ANNUAL=1
B . MONTHLY=12, QUARTERLY=4, ANNUAL=1
C . MONTHLY=3, QUARTERLY=4, ANNUAL=12
D . MONTHLY=1, QUARTERLY=3, ANNUAL=12

Answer: A