An asset requires a diagnostic evaluation every 3 months and an oil change every 18 months. It has been decided to use Job Plan sequencing to generate the work orders at the appropriate interval where Job Plan A represents the 3-month diagnostic and Job Plan B represents the 18-month oil change.
What are the Job Plan sequence values to accomplish this?
A . Job Plan A=1 and Job Plan B=6
B . Job Plan A=3 and Job Plan B=6
C . Job Plan A=1 and Job Plan B=18
D . Job Plan A=3 and Job Plan B=18
Answer: D