Risk acceptance is a component of which of the following?

Posted by: Pdfprep Category: CISM Tags: , ,

Risk acceptance is a component of which of the following?
A . Assessment
B . Mitigation
C . Evaluation
D . Monitoring

Answer: B

Explanation:

Risk acceptance is one of the alternatives to be considered in the risk mitigation process. Assessment and evaluation are components of the risk analysis process. Risk acceptance is not a component of monitoring.