At the conclusion of a disaster recovery test, which of the following should ALWAYS be performed prior to leaving the vendor’s hot site facility?

Posted by: Pdfprep Category: CISM Tags: , ,

At the conclusion of a disaster recovery test, which of the following should ALWAYS be performed prior to leaving the vendor’s hot site facility?
A . Erase data and software from devices
B . Conduct a meeting to evaluate the test
C . Complete an assessment of the hot site provider
D . Evaluate the results from all test scripts

Answer: A

Explanation:

For security and privacy reasons, all organizational data and software should be erased prior to departure. Evaluations can occur back at the office after everyone is rested, and the overall results can be discussed and compared objectively.