Which of the following is an acceptable method for handling positive project risk?

Posted by: Pdfprep Category: CRISC Tags: , ,

Which of the following is an acceptable method for handling positive project risk?
A . Exploit
B . Avoid
C . Mitigate
D . Transfer

Answer: A

Explanation:

Exploit is a method for handling positive project risk.