There are five inputs to the quantitative risk analysis process.
Which one of the following is NOT an input to quantitative risk analysis process?
A . Risk management plan
B . Enterprise environmental factors
C . Cost management plan
D . Risk register
Answer: B
Explanation:
Enterprise environmental factor is not an input to the quantitative risk analysis process. The five inputs to the perform quantitative risk analysis process are: risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets.
Incorrect Answers:
A, C, D: These are the valid inputs to the perform quantitative risk analysis process.