Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
A . SCRUM retrospective
B . Kickoff meeting
C . Budget baseline
D . Risk review
Answer: A
Explanation:
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306