Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Posted by: Pdfprep Category: PK0-004 Tags: , ,

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?
A . SCRUM retrospective
B . Kickoff meeting
C . Budget baseline
D . Risk review

Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306