Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables.
Which of the following should the project manager do NEXT?
A . Determine the flexibility between the project constraints
B . Hold a kick-off meeting with the project team
C . Determine procurement needs to meet the project demands
D . Create the risk register
Answer: C