Fixing a single bug requires the involvement of three teams: Designers, Developers and Testers.
Currently, all the fields that are needed by each of the three teams are together on a single project screen.
As a project administrator, how can you help the teams to easily identify the fields they need?
A . Request a separate issue type and issue type scheme for each team.
B . Use the card colors feature to color-code the fields by team.
C . Make fields available only for the team that needs them.
D . Request individual team screens to be associated with the Edit Issue operation.
E . Group individual fields by team and place them on separate tabs.
Answer: D