Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

Posted by: Pdfprep Category: CAPM Tags: , ,

Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:
A . Continuous
B . Discrete
C . Regulated
D . Arbitrary

Answer: A

Explanation:

Process: 13.1 Identify Stakeholders

Definition: The process of identifying the people, groups,

or organizations that could impact or be impacted by a decision, activity, or

outcome of the project; and analyzing and documenting relevant information

regarding their interests, involvement, interdependencies, influence, and

potential impact on project success.

Key Benefit: The key benefit of this process is that it allows the project manager to identify the appropriate focus for each stakeholder or group of stakeholders.

Inputs