An output of the Direct and Manage Project Work process is:

Posted by: Pdfprep Category: CAPM Tags: , ,

An output of the Direct and Manage Project Work process is:
A . Deliverables.
B . Activity lists.
C . A work breakdown structure.
D . A scope statement.

Answer: A

Explanation:

Process: 4.3. Direct and Manage Project Work

Definition: The process of leading and performing the work

defined in the project management plan and implementing approved changes to

achieve the project’s objectives.

Key Benefit: The key benefit of this process is that it provides overall management of the project work.