Posted by: Pdfprep
Post Date: December 1, 2020
The process of prioritizing risks for further analysis or action is known as:
A . Plan Risk Management.
B . Plan Risk Responses.
C . Perform Qualitative Risk Analysis.
D . Perform Quantitative Risk Analysis.
Answer: C
Explanation:
Process: 11.3 Perform Qualitative Risk Analysis
Definition: The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact.
Key Benefit: The key benefit of this process is that it enables project managers to reduce the level of uncertainty and to focus on high-priority risks.
Inputs
Leave a Reply