When should quality planning be performed?
A . While developing the project charter
B . In parallel with the other planning processes
C . As part of a detailed risk analysis
D . As a separate step from the other planning processes
Answer: B
Explanation:
Quality planning should be performed in parallel with the other planning processes. For example, proposed changes in the deliverables to meet identified quality standards may require cost or schedule adjustments and a detailed risk analysis of the impact to plans. The quality planning techniques discussed here are those used most frequently on projects. There are many others that may be useful on certain projects or in some application areas.