Posted by: Pdfprep
Post Date: October 26, 2020
Which tool or technique is used in the Develop Project Management Plan process?
A . Project management information system (PMIS)
B . Project charter
C . Quality assurance
D . Expert judgment
Answer: D
Explanation:
Leave a Reply