Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
A . Plan Procurement Management
B . Control Procurements
C . Collect Requirements
D . Plan Cost Management
Answer: A
Explanation:
Process: 12.1 Plan Procurement Management
Definition: The process of documenting project procurement
decisions, specifying the approach, and identifying potential sellers.
Key Benefit: The key benefit of this process is that it determines whether to acquire outside support, and if so, what to acquire, how to acquire it, how much is needed, and when to acquire it.
Inputs