Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
A . Direct and Manage Project Work
B . Develop Project Management Plan
C . Plan Quality Management
D . Monitor and Control Project Work

Answer: B

Explanation:

Process: 4.2. Develop Project Management Plan

Definition: The process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project’s integrated baselines and subsidiary plans may be included within the project management plan.

Key Benefit: The key benefit of this process is a central document that defines the basis of all project work.

Inputs