A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

Posted by: Pdfprep Category: CAPM Tags: , ,

A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
A . mitigate
B . accept
C . transfer
D . avoid

Answer: C