Which process determines the risks that may affect the project and documents their characteristics?
A . Control Risks
B . Plan Risk Management
C . Plan Risk Responses
D . Identify Risks
Answer: D
Explanation:
Process: 11.2 Identify Risks
Definition: The process of determining which risks may affect the project and documenting their characteristics.
Key Benefit: The key benefit of this process is the documentation of existing risks and the knowledge and ability it provides to the project team to anticipate events.
Inputs