Posted by: Pdfprep
Post Date: December 14, 2020
Which input to the Plan Risk Management process provides information on high-level risks?
A . Project charter
B . Enterprise environmental factors
C . Stakeholder register
D . Organizational process assets
Answer: A
Explanation:
Leave a Reply