Which tools or techniques are used in the Plan Schedule Management process?
A . Benchmarking, expert judgment, and analytical techniques
B . Statistical sampling, benchmarking, and meetings
C . Negotiations, pre-assignment, and multi-criteria decision analysis
D . Expert judgment, analytical techniques, and meetings
Answer: D
Explanation:
Process: 6.1 Plan Schedule Management
Definition: The process of
establishing the policies, procedures, and documentation for planning,
developing, managing, executing, and controlling the project schedule.
Key Benefit: The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.
Inputs