Scope, schedule, and cost parameters are integrated in the:
A . Performance measurement baseline.
B . Analysis of project forecasts.
C . Summary of changes approved in a period.
D . Analysis of past performance.
Answer: A
Explanation:
Performance Measurement Baseline (PMB). An approved, integrated scope-schedule-cost plan forthe project work against which project execution is compared to measure and manage performance. The PMB includes contingency reserve, but excludes management reserve.