Posted by: Pdfprep
Post Date: December 6, 2020
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A . Identify Risks
B . Control Risks
C . Plan Risk Management
D . Plan Risk Responses
Answer: D
Explanation:
Process: 11.5 Plan Risk Responses
Definition: The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.
Key Benefit: The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed.
Inputs
Leave a Reply