Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

Posted by: Pdfprep Category: CAPM Tags: , ,

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
A . Identify Risks
B . Control Risks
C . Plan Risk Management
D . Plan Risk Responses

Answer: D

Explanation:

Process: 11.5 Plan Risk Responses

Definition: The process of developing options and actions to enhance opportunities and to reduce threats to project objectives.

Key Benefit: The key benefit of this process is that it addresses the risks by their priority, inserting resources and activities into the budget, schedule and project management plan as needed.