Which type of stakeholder engagement does this project require?

Posted by: Pdfprep Category: CAPM Tags: , ,

A project manager is experiencing a project with a high degree of change.

Which type of stakeholder engagement does this project require?
A . Discussing with management
B . Escalating to the sponsors
C . Engaging regularly with stakeholders
D . Engaging only with decision makers

Answer: C

Explanation:

Reference: https://opentextbc.ca/projectmanagement/chapter/chapter-5-project-stakeholders-project­management/