Posted by: Pdfprep
Post Date: December 9, 2020
For the given information:
Activity A, duration 5 days, predecessors: none
Activity B, duration 3 days, predecessors: none
Activity C, duration 6 days, predecessors: A and B
Activity D, duration 7 days, predecessors: B
Activity E, duration 4 days, predecessors: C and D
Activity F, duration 2 days, predecessors: E and B
Which of the following shows the project’s critical path?
A . Start, B, F, Finish
B . Start, B, C, E, F, Finish
C . Start, B, D, E, F, Finish
D . Start, A, C, E, F, Finish
Answer: B
Leave a Reply