One of the outputs of the project schedule is a detailed plan.
What is the main purpose of that detailed plan?
A . It represents how and when the project will deliver the products, services, and results defined in the project scope
B . It creates a formal record of the project and shows the organizational commitment to the project
C . It describes how the scope will be defined, developed, monitored, controlled, and validated
D . It provides the needs of a stakeholders or stakeholder group
Answer: B