Under which circumstances should multiple projects be grouped in a program?

Posted by: Pdfprep Category: CAPM Tags: , ,

Under which circumstances should multiple projects be grouped in a program?
A . When they are needed to accomplish a set of goals and objectives for an organization
B . When they have the same project manager and the same organizational unit
C . When they have the same scope, budget, and schedule
D . When they are from the same unit of the organization

Answer: A