Which estimation method is the project manager using to complete this task?

Posted by: Pdfprep Category: CAPM Tags: , ,

A project team member is estimating the cost of an activity and is checking documentation from previous similar projects.

Which estimation method is the project manager using to complete this task?
A . Bottom-up estimating
B . Three-point estimating
C . Analogous estimating
D . Parametric estimating

Answer: C

Explanation:

Reference: https://pm4id.org/chapter/9-1-estimating-costs/