Which of the following documents should the project manager update as a result of implementing the Plan Risk Responses process?
A . Risk Report
B . Issue Log
C . Assumption Log
D . Risk Management Plan
Answer: D
Explanation:
Reference: https://www.greycampus.com/opencampus/project-management-professional/plan-riskresponses