The project manager has the following information about the estimated duration for an activity:
– Most likely [tM] C 15 days
– Pessimistic [tP] C 20 days
– Optimistic [tO] C 10 days
What is the estimated duration of this activity, according to the triangular distribution technique?
A . 10 days
B . 15 days
C . 12.5 days
D . 5 days
Answer: C