In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with changes?

Posted by: Pdfprep Category: CAPM Tags: , ,

In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with changes?
A . Having control over the planning and delivery of the products without delegating decisions
B . Giving access to information to the team and frequent team checkpoints
C . Selecting different team members to take the project manager role during reviews with stakeholders
D . Asking the control change board to approve changes before notifying the team

Answer: B